RAC undertook a complete re-design of the building once being awarded the contract and achieved the following:

  • Created a basement space with capacity for 24 carparks by elevated the building and using the natural contours of the site, effectively doubling the Gross Floor Area
  • The basement consists of 30 off-form concrete columns; the single-pour suspended deck required 300m³ of concrete; and there are 24 pre-cast panels forming the external walls
  • No major clashes or defects and panels were in place within 6hrs
  • Use of bricks and metal wall cladding to articulate the façade that surpasses the standard ‘industrial shed’
  • Change of construction typology to concrete tilt-panel allowed for a more efficient build in both time and cost
  • An extremely high quality street presence that directly responded to the site by engaging the street

Our efficient processes and neat, quality work ensured there were no cost or time over-runs and the client was moving in prior to the programmed completion date.

 